“We have learnt that the company faces some salary related issues but it is their internal matter, however we have been informed that the issue has been resolved and barring some places the work has been initiated, Designed on a completely decentralised system across 10 zones, the scope of the Rs 491 crore project includes underground sewerage facilities in a radius of 24 sq km area entailing laying a network of 107 km of sewer lines and commission of 10 pumping stations supported by an equal number of sewage treatment plants.” claimed a senior civic official who is handling the project.
The contract is awarded to Supreme Infrastructure India Ltd.
Naya Nagar (Shams Masjid):
Sewerage Pipeline Work, Super Dairy, Shams Masjid Naya Nagar, Mira Road |
Sewerage Pipeline Work, Nihal Corner, Naya Nagar, Mira Road |
Naya Nagar (Hydari Chowk):
Sewerage Pipeline Work, Hydari Chowk, Naya Nagar, Mira Road |
Sewerage Pipeline Work, Hydari Chowk Road, Naya Nagar, Mira Road |
Shanti Nagar ( Jain Mandir):
Sewerage Pipeline Work, Ahinsa Chowk, Jain Mandir, Shanti Nagar, Mira Road |
Sewerage Pipeline Work, Ahinsa Chowk, (Opp.Road) Jain Mandir, Shanti Nagar, Mira Road |
Sewerage Pipeline Work – Contractor Supreme Infrastructure India Ltd. |
Update:
Update – 23rd Feb 2015: There is NO salary for SPML / Supreme Infra’s contract employees for 5 months and therefore MBMC Sewerage Project is completely stopped.
Update: Here is what Mira-Bhayandar Congress Committee says on this issue –
Update – 31 March 2015: Poor road infrastructure in Mira Road due to Sewerage Project work being carried out by MBMC from last 2 years. People here are making a fun of SPML / Supreme Infra by putting following comment:
50% discount for 7 days.
Please Welcome All
Update – 26th April 2015: Road labeling work near Shams Masjid, Opp. Asmita Ascon Acres 1/2/3 started on 4th April and completed on 26th April 2015.
Road Construction Started Near Shams Masjid Naya Nagar – 4th April 2015 |
Road Construction Completed Near Shams Masjid Naya Nagar – 26th April 2015 |
Update – 10th July 2015: Road labeling work in Hydary Chowk started and completed successfully.
Hydary Chowk Mira Road – Road works – July 2015 |