Poor road thanks to Sewerage pipeline work in Mira Road

Mira Road News

Last Updated on 7 years by Mumbai Metro City

Mira Bhayandar Municipal Corporation had started the digging operation to enhanced the Sewerage facilities and improve Water Supply in Mira Bhayandar area. But this work is going on from last one year and road condition in Mira Road is now become pathetic.

“We have learnt that the company faces some salary related issues but it is their internal matter, however we have been informed that the issue has been resolved and barring some places the work has been initiated, Designed on a completely decentralised system across 10 zones, the scope of the Rs 491 crore project includes underground sewerage facilities in a radius of 24 sq km area entailing  laying a network of 107 km of sewer lines and commission of 10 pumping stations supported by an equal number of sewage treatment plants.” claimed a senior civic official who is handling the project.

The contract is awarded to Supreme Infrastructure India Ltd.

Naya Nagar (Shams Masjid):

Sewerage Pipeline Work, Super Dairy, Shams Masjid Naya Nagar, Mira Road

Sewerage Pipeline Work, Nihal Corner, Naya Nagar, Mira Road


Naya Nagar (Hydari Chowk)
:

Sewerage Pipeline Work, Hydari Chowk, Naya Nagar, Mira Road

Sewerage Pipeline Work, Hydari Chowk Road, Naya Nagar, Mira Road

Shanti Nagar ( Jain Mandir):

Sewerage Pipeline Work, Ahinsa Chowk, Jain Mandir, Shanti Nagar, Mira Road

Sewerage Pipeline Work, Ahinsa Chowk, (Opp.Road) Jain Mandir, Shanti Nagar, Mira Road

Sewerage Pipeline Work – Contractor Supreme Infrastructure India Ltd.

Update:


Update – 23rd Feb 2015: There is NO salary for SPML / Supreme Infra’s contract employees for 5 months and therefore MBMC Sewerage Project is completely stopped.

Update: Here is what  Mira-Bhayandar Congress Committee says on this issue –

Update – 31 March 2015: Poor road infrastructure in Mira Road due to Sewerage Project work being carried out by MBMC from last 2 years. People here are making a fun of SPML / Supreme Infra by putting following comment:

Opening Shortly Supreme SPML Restaurant
50% discount for 7 days.
Please Welcome All

Update – 26th April 2015: Road labeling work near Shams Masjid, Opp. Asmita Ascon Acres 1/2/3 started on 4th April and completed on 26th April 2015.

Road Construction Started Near Shams Masjid Naya Nagar – 4th April 2015

 

Road Construction Completed Near Shams Masjid Naya Nagar – 26th April 2015

Update – 10th July 2015: Road labeling work in Hydary Chowk started and completed successfully.

Hydary Chowk Mira Road – Road works – July 2015